Tiling to wet areas have started this week
The 1st coat of paint
Most happy is the kitchen & the underbench sink
So far so good, SS said that I can expect handover in approx 6-8weeks
However a lot of things need fixing still, the LINEN, this is dragging on since the frame stage????? The tradie supposed to come and fix it before Christmas but still not showing up
The plumbing pipe (suppose hide inside the plaster) still visible in bedroom 2 even though plaster is up and archivarch is in, still waiting to be cut/fixed
The brick outside the living area and laundry still incomplete (although it is only a small area) because the support bar (I hope I get the ‘term’ right) is missing/stolen, and due to the size it has to custom made and so I have to wait…
And new issue come up with the mortar, it looks like whoever completed the bricks during NY holiday use different color of mortar, so the color is not match.. SS said that it may not be fully dried so will wait for another week and see what happen, but we had a week of heatwave last week, how come it still not dried.. so another thing on my tracking sheet now..